Wussten Sie, dass 10.000 Stunden „entwickelter Praxis“ als Marke gilt, ab der man ein Experte oder eine Expertin ist? Gute Nachrichten: Jeder gunnercooke Partner und jede gunnercooke Partnerin hat schon mehr als 10.000 Stunden anwaltlich gearbeitet. Sie haben hier also nur mit ausgewiesenen Rechts-Expert*innen zu tun.
A Construction Viewpoint: Practical Completion – what is it?
March 11, 2019
A Practical Completion – An “agreement for lease”. From the name, a layman might assume that this document is the domain of a property lawyer, but as every wise property lawyer knows, it makes sense to get your construction colleagues involved on this one!
Are you sure that construction terms in your Agreement for Lease (AFL) are consistent with the construction documents? An AFL can include a number of construction traps for the unwary, not least the use of Practical Completion (more commonly known as PC) as a trigger for events or payments to occur in relation to the lease. Practical Completion in an AFL and building contract can be the same date… or may turn out not to be, depending on your drafting. How have you defined it? What exactly is PC in a building contract anyway?
PC Triggers Change of Risk and Monies
The achievement of PC has significant consequences under a building contract. This is the point at which much of the risk transfers back to the Employer/Developer. This transfer of risk will usually include a release of retention monies which have been withheld throughout the works, the transfer of insurance obligations and the end of the period in which the contractor may be liable for liquidated damages for delay to the works.
No Single Definition
Most of us in the industry believe that we understand what PC is and what it does but, for such a crucial date in the project, with potentially costly consequences, it is surprising that it has no precise legal definition. It is for you to define what it means in your particular contract.
Vague or ambiguous terms in a construction contract are fuel to the litigious fire which keeps many in the industry warm. There are regular cases in the Technology and Construction Court (TCC) which keep the debate running as to the true meaning of PC in a variety of projects and forms of contract.
In one recent case[1] the contractor, Balfour Beatty, argued that the definition of PC made it impossible for any sectional completion to be reached. They succeeded in the adjudication proceedings, with a declaration from the adjudicator that the liquidated damages provisions under the contract were inoperable and so could not be applied. Balfour Beatty’s argument was based on the literal interpretation of the definitions in the contract:
Practical Completion was defined as “…a stage of completeness of the Works or a Section which allows the Property to be occupied or used…”
Property was: “comprised of the completed Works.”
The adjudicator agreed that:
“The words used in the definition of Practical Completion therefore stipulate that an individual Section only achieves Practical Completion at a stage of completeness which allows the completed Works to be occupied and used. By referring to the completed Works I consider this indicates that all Sections must achieve Practical Completion for any Section to meet the definition of Practical Completion included in the Contract.”
He observed that the definition of PC “may seem illogical however the words used by the parties are clear and unambiguous”.
High Court Chose to Differ
This interpretation was challenged, in the High Court (TCC), by the Employer, the University of Warwick. The TCC disagreed with the adjudicator’s interpretation, stating that it “does not accord with the ordinary meaning of the words used” and placed too much emphasis on the definition of “Property” “at the expense of what the parties plainly meant …. and without regard to the wider context of the other provisions of the Contract and the background known to both parties at the date that they entered into the Contract”.
It seems that common sense won through in that case, but be aware of the pitfalls when drafting or negotiating PC dates and requirements for occupation….your judge may take a different view!